The numbers
| Forecast | Starting point | Where it goes |
|---|---|---|
| IEA, world (Apr 2025) | 415 TWh in 2024, about 1.5% of world electricity | about 945 TWh in 2030; 700-1,700 TWh in 2035 across its four scenarios |
| LBNL, United States (Dec 2024) | 176 TWh in 2023, 4.4% of US electricity | 325-580 TWh in 2028, 6.7-12% of US electricity |
| EPRI, United States (May 2024) | about 4% of US electricity in 2023 | 4.6-9.1% of US electricity in 2030 |
| US utilities, via Grid Strategies (Nov 2025) | about 90 GW of new data-centre peak load by 2030; Grid Strategies thinks about 65 GW is more realistic |
These cover all data centres, including email, video and cloud storage; AI is the part that grows fastest. Forecasts made only a year apart differ by two times or more, which tells you how uncertain this is.
From share prices to gigawatts
Three ways to estimate how much power AI will need, against the new power you think can be built. The revenue comes from our valuation models; everything else is an assumption you can change. Assumption
- Chips the prices imply. The data-centre revenue that NVIDIA's and Broadcom's share prices need each year, turned into chips, then into gigawatts. Chips stay in service for the years you choose.
- Computing the AI labs' revenue implies. OpenAI's and Anthropic's revenue in our models, the share they spend on computing, scaled up to all AI users.
- Usage minus efficiency. How fast AI use grows, minus how fast each unit of AI work gets more energy-efficient.
Revenue:
Chips the prices implyComputing the AI labs' revenue impliesUsage minus efficiencyPower availableBought but not powered
To run the chips that today's prices imply, the world needs about 97 GW of AI data-centre power by 2030 and 174 GW by 2036, up from 30 GW today. With the supply you assume, up to 17 GW of chips (about $628B) would be bought but not powered, at the worst point in 2031.
Change the assumptions
How it works: chips bought each year = data-centre revenue / NVIDIA and Broadcom's share; GW added = chips / spending per GW; power needed = chips still in service. Power available = today's plus the new supply you set, ramping from 60% of your 2030 pace in 2027 to 100% by 2030 (nuclear 0.5 GW a year until 2030). Chips above the power line are "bought but not powered". NVIDIA sales at risk = the yearly rise in unpowered chips, valued at that year's spending per GW, times NVIDIA's share: orders that buyers would delay if they cannot plug them in. Our view
Default anchors: NVIDIA said in August 2026 that it earns about $25B per GW with Grace Blackwell and $40B with Vera Rubin, and about $18B with Hopper. All data centres averaged about 47 GW in 2024 (IEA), and we assume about 30 GW of it is AI today. OpenAI said it ended 2025 with 1.9 GW running. Fact
What has to be true to get there
With our defaults, the market's view needs about 17 GW of new AI data-centre power a year until 2030. For scale: Amazon added about 3.9 GW of power in all of 2025, Microsoft adds about 1 GW a quarter, and only 525 MW of new or upgraded capacity cleared PJM's latest auction, the largest US grid. Fact
- Several sources at once. No single source can add 15-20 GW a year for AI by 2030: gas turbines are sold out, nuclear is slow, solar and wind need storage, and the grid queue takes about five years. Our view
- Faster grid connections. In June 2026 the US energy regulator (FERC) ordered grid operators to revise or justify their rules for connecting data centres and other large loads. Texas now charges a fee and requires disclosure of duplicate requests. Fact
- Flexible data centres. Accepting short cuts at peak times is the quickest way to unlock existing grid capacity. Fact
- Efficiency that does not cut demand. If each unit of AI work gets much cheaper and people do not use more of it, chip sales fall with power. The prices need AI use to keep growing faster than efficiency. Our view
- Somebody pays. Power is a small share of an AI data centre's cost, so tech companies can outbid others; that shifts costs to households and other businesses, which brings political pushback. Our view
Where could the power come from?
| Source | What it offers | The catch | Cost |
|---|---|---|---|
| Gas turbines and plants | The fastest big source today, on site or on the grid. Gas was 46% of the capacity that won PJM's July 2026 auction. | GE Vernova had 116 GW of gas turbine orders and reservations in July 2026 and is mostly sold out to 2030; prices rose 10-20% in half a year. | $48-109 per MWh (combined cycle) |
| Nuclear restarts and uprates | Closed plants reopening and existing ones pushed harder, sold to tech companies on 20-year contracts. | Only a handful of plants can restart. Crane (Three Mile Island unit 1, 835 MW, for Microsoft) aims for 2027. | $141-220 per MWh (new build) |
| Small modular reactors (SMRs) | Factory-built reactors next to data centres, ordered by Google, Amazon and others. | First commercial units are not expected before about 2030; costs are still unknown. | Unknown until the first units run |
| Solar, wind and batteries | Cheapest new energy and quickest to permit in many places. | Weather-dependent: a data centre running day and night needs batteries, backup or a grid behind it. Federal tax credits were cut back in 2025. | $38-78 per MWh (solar); $50-131 with storage |
| The grid and transmission | Connecting to existing power and building new lines. | Grid queues: the median power plant built in 2025 waited 61 months from request to running. ERCOT in Texas has 474 GW of large-load requests, about 90% data centres, five times its peak demand. | Shared by all customers |
| Flexibility | Data centres that cut use for a few hours at grid peaks can connect years earlier. | Duke University found US grids could add 76-126 GW of new load if it accepts cuts in 0.25-1% of hours. Training jobs can pause; chat and search cannot easily. | Cheap, but needs new contracts |
| Moving the computing | Building where power is spare: the Gulf, Nordics, Canada, and (one day) space. | Export rules, delays sending data far away, and politics. Orbital data centres are a moonshot on the SpaceX page. | Varies |
Fact Costs are Lazard's unsubsidised ranges per MWh for new US plants (June 2025). Anthropic estimated in July 2025 that the US AI industry needs at least 50 GW of new power by 2028.
Using less: efficiency and adoption
Each new chip generation does far more AI work per watt, and software tricks (smaller models, better algorithms) cut energy further. But every time AI gets cheaper, people and companies use more of it, the Jevons paradox. Whether total power use rises or falls depends on which grows faster: use or efficiency. Try it with the "Efficiency surprise" and "Demand slows" buttons above. Our view
Adoption matters as much as efficiency. Chat answers use little energy each; AI agents that work for hours, video generation and reasoning models use many times more per task. A shift from chat to agents can multiply demand even if the number of users stops growing. Our view
Stranded GPUs: chips with nowhere to plug in
When chips arrive faster than power, they wait: in warehouses, in half-finished buildings or in racks that are switched off. This is already happening.
- Microsoft (Nov 2025). CEO Satya Nadella said the biggest issue is not a glut of computing but power, and that Microsoft had chips "sitting in inventory" it could not plug in. Fact
- Amazon (Oct 2026). Business Insider reported that AWS takes ownership of NVIDIA GB300 racks before its sites can power them, with about $5B of racks in US warehouses in August and about $3B more a month expected. Amazon called staging hardware near sites best practice. Fact
- Santa Clara (2025). Two finished data centres of nearly 100 MW in NVIDIA's home town were reported idle because the city's grid could not yet supply them. Fact
- Capacity sold out. Amazon says AWS power stays short through 2027 and reserves blocks of hundreds of megawatts to 1 GW well in advance; Microsoft says it remains capacity constrained. Fact
What it means for NVIDIA
Sales are booked when chips ship
NVIDIA records revenue when it delivers, so racks waiting in a warehouse still count. The risk shows up later, as smaller or delayed orders once buyers hold too much unplugged hardware. Our view
Power, not money, caps the market
If only so many gigawatts can be connected each year, NVIDIA's growth is capped by gigawatts times its revenue per gigawatt. That is why it pitches revenue per GW: $18B for Hopper, $25B for Grace Blackwell, $40B for Vera Rubin. Fact
Best chips win when power is scarce
With a fixed power budget, a data centre earns the most with the chips that do the most work per watt. That supports prices for NVIDIA's newest chips, but makes older ones worth less sooner. Our view
NVIDIA is now in the power business
NVIDIA guarantees up to $108.5B of partners' data-centre obligations, $105B of it for SB Energy's sites, and signs leases it plans to pass to others. If power projects slip, those guarantees tie NVIDIA to its customers' problems. Fact
Signals to watch: NVIDIA's receivables and inventory, customers' "construction in progress" (buildings not yet running), cloud capacity comments on earnings calls, gas turbine and transformer lead times, PJM and ERCOT auction results, and rental prices for AI chips.
Who pays for the power?
For a tech company, power is cheap next to chips: with our defaults a year of electricity for 1 GW costs about $1B, against about $30B of chips. So AI buyers can outbid everyone else for scarce power. Assumption
PJM's auction for mid-2028 to mid-2029 cleared at its price cap of $325 per MW-day and still came up 6.8 GW short of its reliability target; without the cap it would have cleared at about $555. The market monitor attributes $6.3B of the $16.4B cost, 38%, to data centres. Those costs reach household bills in 13 states. Fact
Lexicon: power words
- Watt, megawatt (MW), gigawatt (GW)
- Power: how much electricity something draws at one moment. A GW is a billion watts, about one large power plant. AI campuses are now planned at 1-5 GW each.
- Watt-hour, terawatt-hour (TWh)
- Energy: power used over time. 1 GW running all year is 8.76 TWh. The US uses about 4,000-4,500 TWh a year.
- IT load vs facility power
- IT load is what the chips and servers draw; facility power adds cooling and losses. The ratio is called PUE, about 1.1-1.4 for new AI sites.
- Interconnection queue
- The waiting list to connect a power plant or a big customer to the grid. Most requests in it are never built.
- Capacity auction
- Where grid operators such as PJM pay power plants to be available at peak times. High prices signal a shortage, and the cost lands on everyone's bills.
- Behind the meter
- Power made on site (often gas turbines) and used directly, without waiting for a grid connection.
- Stranded or dark GPUs
- AI chips that have been bought and delivered but are not running, usually because the building has no power or cooling yet.
- Perf per watt, tokens per watt
- How much AI work a chip does for each unit of power. When power is the bottleneck, this decides how much revenue a data centre can earn.
- Jevons paradox
- When something gets more efficient and cheaper, people often use so much more of it that total consumption rises.
Questions people ask
How much electricity does AI use?
The IEA estimates all data centres used about 415 TWh in 2024, about 1.5% of the world's electricity, and that AI servers are the fastest-growing part. Our model assumes AI data centres run about 30 GW today, roughly 200 TWh a year at the usage we assume.
How much power will AI need by 2030?
Forecasts range widely. The IEA's base case has all data centres at about 945 TWh in 2030; US utilities forecast about 90 GW of new data-centre load by 2030. Our model turns today's AI share prices into about 97 GW of AI data-centre power worldwide by 2030.
What are stranded GPUs?
AI chips that are bought but not running, because the data centre has no power or cooling yet. Microsoft's CEO said in November 2025 that chips were "sitting in inventory" that he could not plug in, and in October 2026 Business Insider reported Amazon was storing billions of dollars of NVIDIA racks in warehouses waiting for power.
Is power a risk for NVIDIA?
Power limits how many chips customers can install each year, whatever their budgets. If chips pile up unplugged, orders get delayed. It also pushes buyers towards the chips with the most work per watt, which so far favours NVIDIA's newest products. See the stranded chips section above.
Value the companies behind the numbers: NVIDIA · Broadcom · OpenAI · Anthropic · CoreWeave · Oracle · Microsoft · Amazon · Alphabet · Is AI a bubble?
Sources
- IEA: Energy and AI (April 2025)
- IEA: Electricity Mid-Year Update 2026 (July 2026)
- LBNL: 2024 United States Data Center Energy Usage Report (Dec 2024)
- LBNL: Queued Up, 2026 edition (June 2026)
- EPRI: Powering Intelligence (May 2024)
- Grid Strategies: National Load Growth Report (Nov 2025)
- Utility Dive: PJM 2028/29 capacity auction hits the price cap, reserve shortfall grows (July 2026)
- Texas Governor's review of data centres seeking ERCOT connection (Aug 2026), via Butler Snow
- Turbomachinery: GE Vernova gas turbine backlog hits 116 GW (23 July 2026)
- World Nuclear News: Constellation seeks help for 2027 Crane restart (2026)
- Duke University Nicholas Institute: Rethinking Load Growth (Feb 2025)
- Lazard: Levelized Cost of Energy+ (June 2025)
- NVIDIA Q2 fiscal 2027 results and call (26 Aug 2026): revenue per gigawatt
- Magica: what NVIDIA's $40 billion per gigawatt claim means (Aug 2026)
- DCD: Microsoft has AI GPUs "sitting in inventory" for lack of power (Nov 2025)
- Business Insider via American Bazaar: Amazon's Nvidia servers wait in warehouses for power (Oct 2026)
- Tom's Hardware (Bloomberg): Santa Clara data centres sit idle waiting for power
- DCD: OpenAI says it has secured 10 GW of capacity (2026)
- DCD: Microsoft brings 1 GW of capacity online in a quarter, again (July 2026)
- Amazon Q3 2026 results (29 Oct 2026)
- Anthropic: Build AI in America (July 2025)
- FERC orders on large-load interconnection (18 June 2026); NVIDIA 10-Q for the quarter to 26 July 2026 (guarantees); Amazon Q2 2026 call (power short through 2027); Microsoft FY2026 Q4 call (capacity constrained).
Not investment advice. Stonkometer is an educational calculator, not investment advice. Valuations depend entirely on the assumptions you choose. We are not a broker or adviser, and nothing here is a recommendation to buy or sell any security. Do your own research and consider a licensed adviser. Full disclaimer